Gloucester Police HQ

Gloucester Police HQ

The largest Closed Loop system in the UK
150 boreholes, each 98m deep
UP to 860kW of cooling & 640kW of heating
With estimated savings of £60,000 per year, the system is consistently achieving a CoP above 6 and exceeding efficiency targets of more than 30%.

Embassy Court, London

Embassy Court, London

Residential apartment block, central plant room
Energy Piles and boreholes, plus a dry cooler system for additional cooling
100 Energy Piles and 40m boreholes
202kW of heating & 371kW of cooling
Precision drilling was required, as the building lies close to the London Underground.

Alexandra Park School, London

Alexandra Park School, London

System: Vertical, Closed Loop System
Size: 120kW Cooling
Collector type: 20 boreholes
Depth: 100m
Completed: 2004

Chelsea Building Society HQ

Chelsea Building Society HQ

System: Vertical, Closed Loop
Size: 490+380kW Cooling
190+290kW Heating
Collector type: 108 boreholes
Depth: 98m
Completed: 2006

Haybridge High School, Birmingham

Haybridge High School, Birmingham

System: Vertical, Closed Loop
Size: 4 x EKW17 Heating & Cooling
Collector Type: 12 Vertical Closed Loop Boreholes
Completion: 2007